Data center regulations in Florida

Graded Substantial and tightening. 19 laws, orders, rulings and local actions, each with its source, reviewed 4 November 2026.

Reviewed 4 November 2026 · Part of the Data Center Rulebook

2026 law makes 50 MW loads pay full cost; counties pause

Substantial↑ TighteningGrid: Southeast utilities19 items
15in force
4pending
8local pauses
narrowedtax break
3.4combined index (5 most)
8.9cper kWh, industrial
4 November 2026reviewed
Regulation3.8 / 5
  1. Grid connection3

    SB 484 (1 July 2026) bars tariffs that block curtailment, and FPL's Nov 2025 terms make 50 MW loads fund a study, a substation and 100% of new generation.

  2. Power rates5

    SB 484, in force 1 July 2026, is a statewide full cost-of-service law for 50 MW loads; FPL's compliant tariff adds 20-year terms, minimum bills and exit fees.

  3. Siting and land use4

    Pauses in Palm Beach, Sarasota, Nassau, Manatee, Marion and Pasco and Volusia's 50 MW bar (20 Oct 2026) reach the Tampa and Orlando markets; Miami-Dade open.

  4. Tax treatment3

    HB 7031, effective 1 Aug 2025, narrowed the sales tax exemption to facilities of 100 MW or more with no grandfathering; it runs to June 2037.

  5. Permits and water4

    SB 484's water rules (2026) deny permits that harm water resources, require reclaimed water and force a hearing above 100,000 gallons a day.

Scored on rules in force, 1 to 5. 5 is the most regulated. Pending rules set the arrow.

Florida enacted SB 484 in May 2026. It requires the Public Service Commission to make customers of 50 MW or more bear their full cost of service, protects local zoning authority, cuts data center projects out of the 12-month confidentiality extension for economic development records and tightens water permitting. The four investor-owned utilities filed tariffs or compliance statements by 1 October 2026; FPL says its 20-year large-load tariff approved in November 2025 already complies, and PSC staff have recommended that Duke Energy Florida's tariff, the first filed under the act, be denied as filed and refiled. The sales tax exemption survives through June 2037 but since August 2025 only for facilities of 100 MW or more. More than a dozen counties have adopted moratoria or bans, including 12-month pauses in Nassau, Sarasota, Palm Beach, Manatee, Marion and Pasco and a Volusia County bar on applications of 50 MW or more.

Outlook for the next year

Republican Byron Donalds, projected the winner by the Associated Press on 3 November 2026, succeeds Ron DeSantis in January 2027 with former state senator Bryan Avila, the SB 484 sponsor, as lieutenant governor; Donalds opposes a statewide moratorium, says local governments decide whether data centers are built, and will receive the state study of data center impacts due 1 July 2027. Republicans keep both chambers for the session starting in March 2027 but unofficial results show they lost the House supermajority and may lose the Senate's, which matters mainly for tax and procedural votes rather than for data center bills, which passed SB 484 with wide bipartisan margins. The Public Service Commission voted 5-0 on 3 November 2026 to reject Duke Energy Florida's large-load tariff (Docket 20260064-EI) as not shown to comply with SB 484, and Duke is expected to refile; Tampa Electric's tariff, filed 30 September 2026, expects a decision in late 2026 or early 2027, and FPL's 1 October compliance statement is still to be reviewed. Edgewater voters wrote a ban on new data centers into the city charter on 3 November. County pauses cover Palm Beach, Sarasota, Nassau, Manatee, Marion and Pasco, Volusia has barred applications of 50 MW or more in unincorporated areas since 20 October 2026 and the city of Alachua adopted a one-year pause in late October; Pasco's pause runs to May 2027 and Marion's to September 2027. The Southwest Florida Water Management District must still approve the water supply for the Fort Meade campus.

After the 3 November 2026 election
  • Governor Byron Donalds (R). Donalds opposes a statewide data center moratorium, says the state study is already underway, and says of SB 484 that "it is now state law in Florida that if local governments say no data center, then no data centers" and that he will ensure utility bills do not rise for customers of rural cooperatives. fox13news.com
  • Legislature Republican both chambers, control changed. Republicans keep majorities but unofficial results show them losing about 15 House seats and the two-thirds supermajority (80 of 120) they held, and the Senate supermajority (27 of 40) was in doubt with at least one race near recount margins. cbsnews.com
  • Commission Public Service Commission members are appointed by the governor; no seats were on the ballot. On 3 November 2026 the PSC voted 5-0 to reject Duke Energy Florida's large-load tariff as not shown to comply with SB 484. chronicleonline.com
  • Edgewater charter amendment prohibiting new data centers (Edgewater (Volusia County), passed) Writes into the city charter a ban on approving, building, expanding or operating new data centers in the city, locking in a ban the City Council adopted earlier in 2026; early results showed at least 77 percent in favor. forbes.com

Results as called on 4 November 2026. Positions are the winners' own statements; a platform is not a rule and does not change the grade.

Does Florida have a data center moratorium in force?

No statewide moratorium, but 8 local pauses are in force as of 4 November 2026, in City of Alachua, Manatee County, Marion County, Nassau County, Palm Beach County, Pasco County and elsewhere. Proposals and expired pauses are not counted.

Is Florida tightening or loosening its rules on data centers?

Tightening. Florida is graded Substantial, which means binding new costs, siting limits or disclosure rules on new data centers. 2026 law makes 50 MW loads pay full cost; counties pause. The outlook above says what is pending.

Which grid operator covers Florida?

Florida sits in Southeast utilities. The grid operator decides how a new large load is studied, what it must bring or pay, and whether it can be curtailed first; the state decides siting, permits, tariffs and incentives.

Has Florida cut its data center tax incentive?

Yes. Florida has paused, narrowed or ended a data center incentive in 2025 or 2026: HB 7031: sales tax exemption limited to 100 MW and above.

How regulated are data centers in Florida?

On Genloop's five-line rubric (1 least regulated, 5 most) Florida scores grid connection 3, power rates 5, siting and land use 4, tax treatment 3, permits and water 4, a mean of 3.8. The most regulated line is power rates: SB 484, in force 1 July 2026, is a statewide full cost-of-service law for 50 MW loads; FPL's compliant tariff adds 20-year terms, minimum bills and exit fees.

What did the 3 November 2026 election change for data centers in Florida?

Byron Donalds (R) won the governor's race. Donalds opposes a statewide data center moratorium, says the state study is already underway, and says of SB 484 that "it is now state law in Florida that if local governments say no data center, then no data centers" and that he will ensure utility bills do not rise for customers of rural cooperatives. Legislature: Republican both chambers, control changed. Binding measures passed: Edgewater charter amendment prohibiting new data centers (Edgewater (Volusia County)). The arrow is tightening: SB 484 implementation continues under a governor who backs local control; the PSC rejected Duke's first tariff on 3 November and county pauses keep spreading.

Every item, newest first

19 items: each is a law, order, tariff, ruling, utility action or local decision that changes what a data center must do, pay or disclose, or where it may be built. Failed and pending measures are marked. Each links to its source.

  1. LocalEdgewater (Volusia County)Nov 2026moratoriaApproved, not yet effective

    Edgewater voters write data center ban into city charter

    On 3 November 2026 Edgewater voters approved a charter amendment that prohibits new data centers from being approved, built, expanded or operated in the city, making permanent a ban the City Council adopted earlier in 2026. Early unofficial results showed at least 77 percent in favor.

    Source: forbes.com
  2. UtilityFlorida Power & LightOct 2026costs and tariffsIn force

    FPL tells PSC its large-load tariff already complies with SB 484

    FPL's Large Load Contract Service terms, approved in November 2025 as part of its 2026 to 2029 rate plan, require applicants to fund an engineering study, pay 100 percent of new generation built for them, build their own substation, meet a minimum bill on reserved capacity, sign a 20-year minimum contract and pay an exit fee. The PSC still has to review the compliance filing.

    Source: wusf.org
  3. LocalManatee CountyOct 2026moratoriaIn force

    Manatee County adopts one-year data center moratorium

    Commissioners voted unanimously on 28 July 2026 to have staff draft a moratorium on data centers and other large-load projects. On 8 October 2026 the board adopted a one-year moratorium that pauses the acceptance, processing and approval of new data center projects while the county studies effects on energy, water, infrastructure and communities and writes rules. Commissioners said no data center projects were planned in the county at the time.

    Source: mysuncoast.com
  4. LocalVolusia CountyOct 2026moratoriaIn force

    Volusia County bans data centers of 50 MW or more in unincorporated areas

    The county council voted 6-0 on 20 October 2026 for an ordinance under which the county will not accept, process, review or approve applications for data centers with an anticipated monthly peak load of 50 MW or more in unincorporated areas. Projects under 50 MW may still apply but go through staff review, a zoning and regulation committee and a council vote. Cities inside the county set their own rules.

    Source: mynews13.com
  5. LocalCity of AlachuaOct 2026moratoriaIn force

    City of Alachua one-year moratorium on data centers

    City commissioners approved a one-year moratorium 5-0 on second reading in late October 2026, after a 4-1 first reading earlier in the month. It pauses applications and non-disclosure agreements involving data centers within the city.

    Source: wcjb.com
  6. UtilityTampa ElectricOct 2026costs and tariffsPending

    Tampa Electric large-load tariff filing

    Tampa Electric filed its large-load tariff with the PSC on 30 September 2026 under SB 484. Large-load customers would pay for all electric system upgrades needed to serve them and contribute to the cost of maintaining the broader system. The utility says it serves no large-load customer today and expects a PSC decision in late 2026 or early 2027.

    Source: baynews9.com
  7. RegulatorOct 2026costs and tariffsPending

    PSC implementation of SB 484

    Each investor-owned utility (FPL, Duke Energy Florida, Tampa Electric and Florida Public Utilities) had to file a tariff complying with s. 366.043 for PSC approval by 1 October 2026. The PSC may approve tools such as minimum bills, exit fees and credit support but the act sets no rulemaking deadline. Municipal utilities and cooperatives such as JEA, OUC and Gainesville Regional Utilities are not covered.

    Source: flsenate.gov
  8. RegulatorDuke Energy FloridaOct 2026costs and tariffsPending

    Duke Energy Florida large-load tariff: PSC staff recommend denial, vote 3 November 2026 (Docket 20260064-EI)

    Duke filed on 22 April 2026 for customers with 50 MW or more of firm load at one site: a 20-year contract, take-or-pay minimums of 75 to 85 percent of contracted capacity, credit support, two years' notice to leave and an exit payment of three years of minimum bills plus the net book value of new facilities, with a dedicated rate schedule to take effect 1 January 2028. Hearings ran on 25 and 26 August 2026. On 22 October 2026 PSC staff recommended that the Commission deny the tariff as filed with leave to refile, saying the proposal does not yet ensure each large-load customer bears its full cost of service, with an alternative of interim approval widened to every customer meeting the 50 MW definition. The Commission votes on 3 November 2026; if denied, Duke would have 10 business days to refile.

    Source: mgrid.org
  9. LocalPalm Beach CountySep 2026moratoriaIn force

    Palm Beach County one-year moratorium on data centers of 50 MW or more

    Commissioners voted 6-0 on 24 September 2026 to stop accepting or approving zoning requests for data centers with peak load of 50 MW or more in unincorporated areas for up to a year. In July they rejected a large expansion of Project Tango, which keeps a smaller 2016 approval.

    Source: cbs12.com
  10. LocalMarion CountySep 2026moratoriaIn force

    Marion County 12-month moratorium on data centers of 50 MW or more

    The Board of County Commissioners adopted an ordinance 5-0 on 15 September 2026 that freezes large commercial data centers expected to draw 50 MW or more at maximum demand in unincorporated Marion County for 12 months from the effective date, or sooner if new land development or comprehensive plan rules are adopted. Facilities under 50 MW may still be reviewed as special-use permits, and school and hospital IT facilities are exempt.

    Source: 352today.com
  11. LocalSarasota CountyJul 2026moratoriaIn force

    Sarasota County 12-month moratorium

    Sarasota County adopted a 12-month pause on data centers in July 2026 to study impacts and write permanent rules.

    Source: baynews9.com
  12. LocalPasco CountyJul 2026moratoriaIn force

    Pasco County 12-month moratorium on data centers

    Commissioners passed a 12-month moratorium unanimously in July 2026 on building permits, rezonings and site plans for new data centers in unincorporated Pasco County, retroactive to 27 May 2026 when the hearing was first advertised. The exemption for small facilities was lowered to 2.5 MW from a proposed 10 MW, and a proposed 19.9 MW data center near I-75 and State Road 52 falls inside the pause.

    Source: tampabaybeacons.com
  13. LocalNassau CountyJun 2026moratoriaIn force

    Nassau County 12-month moratorium

    Commissioners approved a 12-month moratorium in June 2026 on accepting, reviewing or approving data center applications, including rezonings and site plans, while a committee studies impacts.

    Source: news4jax.com
  14. State lawMay 2026costs and tariffsIn force

    SB 484 (Chapter 2026-65): full cost of service for loads of 50 MW or more

    Signed 7 May 2026 after votes of 31-6 and 92-16; most provisions took effect 1 July 2026. Customers with an anticipated monthly peak of 50 MW or more at one site must bear their full cost of service and may not split loads to avoid it. Tariffs may not block curtailment for grid stability, and utilities may not knowingly serve large loads controlled by foreign countries of concern.

    Source: flsenate.gov
  15. State lawMay 2026siting and zoningIn force

    SB 484: local control and shorter confidentiality for data center deals

    Local governments keep comprehensive planning and land development authority over large-load customers, and a large load customer may not be treated as an electric substation under s. 163.3208; these provisions took effect on signing, 7 May 2026. The act also bars data center projects from the 12-month extension of confidentiality for economic development information under s. 288.075, so project details become public sooner.

    Source: flsenate.gov
  16. State lawMay 2026waterIn force

    SB 484: water permitting for large-scale data centers

    Water permits may not be issued if the use would harm water resources or conflict with local zoning. Reclaimed water must be used where available and feasible, and applications averaging 100,000 gallons a day or more need detailed source and conservation plans and a hearing.

    Source: news4jax.com
  17. LocalFort Meade (Polk County)Apr 2026siting and zoningIn force

    Fort Meade approves 20-year development agreement for Stonebridge data center

    Fort Meade's planning board approved Stonebridge's plan for 1.9 million square feet, expandable to 4.4 million, on 7 April 2026 despite a petition of about 500 residents. On 14 April 2026 the city commission voted unanimously for a 20-year development agreement covering the 1,300-acre site. Florida Commerce Secretary Alex Kelly wrote to the city on 17 April 2026 calling the proposal fundamentally flawed on water and energy grounds. The Southwest Florida Water Management District governing board must still approve the water supply for the project.

    Source: baynews9.com
  18. LocalSt. Lucie CountyOct 2025siting and zoningPending

    Sentinel Grove Technology Park (Project Jarvis)

    The county planning and zoning commission voted 4-2 in October 2025 to recommend against a plan amendment for a 1,218-acre campus near Fort Pierce planned for a first 1,000 MW. In February 2026 a county commissioner said the developer appeared to have pulled back ahead of the state data center law, though it had not formally withdrawn. No county commission vote has been reported.

    Source: wflx.com
  19. State lawAug 2025incentivesIn force

    HB 7031: sales tax exemption limited to 100 MW and above

    Passed 30 June 2025 and effective 1 August 2025. The data center sales tax exemption now applies only to facilities with a critical IT load of 100 MW or more, up from 15 MW, with no grandfathering for smaller sites.

    Source: ryan.com